Reno@B4 Maisonette | Updates

Although it may look like a warzone, but there was some stuff done over the Christmas, New Year and CNY. The plumbing works in the toilets are almost 70% completed, tiling in the toilets completed too. Electrical wirings have all been pulled to their respective places and the aircon trunking is up too.

minor patching up works for the walls and ceiling are in progress. Plasterboards are delivered to site too.



 above: Tiling completed for bathroom on the lower floor





above: kitchen half height wall up too!

Thursday, December 06, 2018

Reno@B4 Maisonette - Kick off meeting

 meeting on site to go through some items with both home owner and contractor.
Hacking and clearing of debris has completed. 
The upper floor is super spacious now with all the walls hacked off.