Maisonette Serangoon - #11 Wardrobe in progress

Today we'll have more updates on wardrobes!


Ritey, just an overall look on the kitchen top again...

Both are wardrobes to 2nd storey guest rooms, one for their future baby, the other is for their mother.
The missus of the house has chosen a deep brown timber laminate for the interiors.
The sliding door will be finished in white.
The parquet are original, just needs another round of sanding and polishing once all the interior works are completed. Should look fresh and new!

Here's a look at the 2nd storey toilets vanity works: both toilet cabinetry are almost there, leaving the mirrors and counter top and lastly the sink and taps.
The toilet in white tiles is the common toilet on the 2nd storey, we kept the existing wall tiles to save cost and re-tile the flooring plus add new electrical works.
The master toilet is the one with the grey wall tiles and the Vanity counter will be flushed with top and bottom lights for a warm ambiance.

some cleaning up after the carpenters have left the premises....

2nd storey master: Wardrobe almost all in now, leaving the sliding doors and drawers.

Shoe cabinet under the window also completed.


last but not least, the glass sliding doors are installed!

Wednesday, December 21, 2011

Maisonette Serangoon - #10 Kitchen in Progress!

Today is all about KitchenWerkz!


most of the kitchen carcass is 80% installed.
Soon the counter top subcon will be coming in to measure the top, followed by the backsplash subcon.

breakfast counter cabinetry is almost there too!

Glass sliding door between Kitchen and yard are almost there!

2nd storey Master: Wardrobe shaping up too.

downstairs is a war zone...the parquet subcon, the cabinetry subcon, the electrician, the plumber and the painter! It's a party here man.

Track in for sliding door to yard from Living installed too.

see how packed the upstairs guest rooms are too? All the toilet cabinetry are waiting to be installed!

Saturday, December 17, 2011

Maisonette Serangoon - #9 plasterboard ceiling up

Today's updates are mostly on the ceiling and plasterboard areas:

here's looking at the living room plasterboard area where the feature wall cum tv will be.

kitchen updates: Kitchen wall tiles all plastered up, looking very spiffy now! ^_^
Looks so much neater compared to the flowery wall tiles earlier.
*sigh*
I just love simple clean lines.

some updates on the 1st storey guest room: floor tiles all laid and electrical wirings all up
1st storey toilet: zoom in on the wall tiles here - eggshell kind of pattern we are using here...mrs finds them rather cute and she says she's super duper happy with the small toilet outcome!
Plus the box up also done to conceal the pipe works.

2nd storey guest toilet updates: the hole in the wall is finally finished. And plumbing works are completed.

zoom in on the track to receive the glass partition and the plumbing works to receive the sanitary fittings.
Love LOVE the textured wall tiles which we proposed for the owners...think they are loving it too!!!!

here's a zoom in on the ceiling box to the right, making things looking neater!

here's a box up at the Guest toilet entrance area where we will put the water heater.

box up ceiling in the Guest toilet area....

Master room: False ceiling up too! Next will be the light fittings to create the ambience for the lovely couple!

window area in master also boarded up as this will be the tv console area, to the right is the toilet.



yard: walls are plastered up, looking neat here! And previous dustbin removed to make way for new one!



Living room false ceiling up to receive pelmet and light fittings.

kitchen cabinetry are moving here!!! WEE!

Monday, December 12, 2011

Maisonette Serangoon - #8 Laying tiles

Here are more updates on our Maisonette reno works:

men laying the floor tiles in the living room

here's at the little store area underneath the staircase



1st storey toilet updates: Floor and wall tiles all up

1st storey Kitchen: Electric works installed


2nd storey master toilet: Wall and floor tiles laid


2nd storey guest toilet: Same thing here, wall and floor tiles laid.
We have chosen the same wall and floor tiles for the upper toilets.
Only the 1st storey toilet has a different wall tile as it's smaller and better to have a light colour wall tile to brighten the little toilet up.

concrete plinth laid to receive the kitchen cabinetry.
Mrs of the house said that her MIL does heavy washing in the kitchen, so it's better to lift the kitchen cabinetry.

shifted the utility box from the guest room to just beside the main entrance gate for convenience and easy maintenance.

All switches in!

Saturday, December 03, 2011

Stirling HDB Terrace - #339 wine markers

cutesy stuff for your kitchen - wine markers!

Maisonette Serangoon - #7 Aircon ducting In

2 more days and here are the updates!


the rack for a system 3 hung up to receive the compressor.

walls are being plastered in the kitchen

Here's looking out from the kitchen

Sis room fully plastered wall and kitchen wall plastered too!

Here's looking from the yard and you can see the kitchen wall is done now...waterproofing laid to the kitchen floor before the floor tiles goes on top...this should take another 24hours or so.

staircase store room...all plastered!

here's looking at the pile of sand in the living room

Upstairs: Master > A/C shifted to top of toilet door.

Upstairs: Guestroom 2> A/C shifted to above door

Upstairs: Guestroom 1> A/C shifted to above door

Downstairs: Here's looking into the kitchen area....

Upstairs common toilet > wall erected



Upstairs Master toilet > wall plastered and waterproofing laid before floor tiles to go on top!

Downstairs: an internal view in sis's room.