Friday, July 31, 2020

Reno@31Ipoh2 | Pre Reno Photos

 Hello Everyone!!!
We are embarking on a new project at Versilia and this will be our 2nd project at this condominium. Talk about fate! When we first received this project, we were thinking, hey this floorplan looks so similar and it was only when we met the home owners who disclosed the address then we realised that we have already done one unit here.

But it will be a totally whole different experience and reno vibes because all our homeowners have their own living styles and needs. Reno is going start in a the next 2 weeks and we are here to recce the place first.

This is was one of the few projects which the design was halted during the circuit breaker and now we are able to embark on the physical change of works. Exciting times!!!








Have a good long weekend folks!
xoxo
velle

Friday, July 24, 2020

Reno@TS | Bathroom






Reno@TS | Bathroom

Hello everyone! 

It has been months since my last update. While we have been busy just concentrating on refining our designs, we actually managed to complete a mini renovation on a bathroom just before circuit breaker started in April. Once the extended circuit breaker was lifted in June, we managed to arrange for quick photoshoot. And here is our mini project on the bathroom.

However due to the worldwide COVID 19 situation, we have quite a few renos which just had to halt during the past few months and a few which we handed over their keys but unfortunately, the home owners are currently waiting for their overseas furniture to be shipped in and so till date, we are still unable to take any home photoshoots.

Now that we are already in Phase 2, we have resumed those projects under renovations and going to start some too!!

Exciting times again!!!

Keep safe everyone and I will try to update my blog as fast as I can.

xoxo
velle

ps: i'm on childcare leave today as this week is the school holidays and I'm planning to bring the kids out for a breather.

Thursday, July 23, 2020

Reno@Anchorvale | Restart Works!

Even though we are into Phase 2, there still many restrictions going on, not enough manpower, workers from malaysia are unable to enter into Singapore; the factories in malaysia are not open etc. These all affect our carpentry works and I'm really glad to say we are finally able to see some work starting at our reno at Anchorvale!!!

Today our local carpenters (yes we had no choice but to switch, because time waits for no man) and usual electrician are on site, discussing how to conceal the wirings and install the carpentry in the kitchen.
above: beautiful open shelf. The backing conceals the pipes...once it is done, you wouldn't even know that there are 2 big pipes.