Saturday, October 13, 2018

Home@Stirling - Goodbye

we sold our place and are moving out of Stirling today.
Goodbye to our 1st home and all the wonderful memories we had.

Thursday, October 11, 2018

Reno@432B - Hollowblock walls

 most of the hollowblock walls are up. Leaving the dry wall partition next.

 above: master bath wall. This used to be the utility bathroom.

above: The old walls, beams and ceiling had the popcorn spotty look which we have plastered over. Now all the existing walls have a smooth finish to it.
above: some of the rooms starting to take form. Not very enclosed yet, but once the dry walls start to come in, you probably will see more spaces taking shape.





Saturday, October 06, 2018

Reno@Spottiswoode - Tiles Selection

2 different pattern tiles. 
One for the master bathroom and another for the entrance foyer.

Friday, October 05, 2018

Reno@432B - Progress Updates

 above: Today the ceiling board has been torn down!



 above: think the workers have broken all the bottom half glass lourve windows


 above: skirting gone too!







above: existing window sill height is different. O_O

Reno@432B - Setting out


The things we do that most people don't see. 
Getting the first step right. Marking out the future walls and floor.

Wednesday, October 03, 2018

Reno@432B - Hacking progress

 above: corridor leading to the yard. Grid ceiling board not yet demolished.
above: current toilet. At least all the sanitary ware have been removed, the wall and floor tiles hacked away too.
 above: current state of the existing flooring.




not much to see. Hopefully we get to see more progress in the coming weeks.