Saturday, July 05, 2014

Reno@Bt Timah - Tiling works

 Brick wall in the living room up! Lots of terracota roof tiles on site (left of photo)
 Helper's room walls are erected.
 staircase railing is up!
 Photo progress of the bathrooms upstairs.
 
List of works to be completed - so many and so little time!
  • tiling works - 50% 
  • aircon trunking - 90%
  • electrical - 50%
  • plumbing - 50%
  • new roof
  • new windows - 80%
  • false ceiling and partition works 
  • parquet
  • painting
  • carpentry
  • glass
  • countertops