Saturday, August 23, 2014

Reno@B Maisonette - Walls hacked, what's next?

All the floor and wall tiles have arrived on site. Monday we are going to start erecting all the new walls and simultaneously lay the wall and floor tiles too. Some of the window frames are here too!
 All the kitchen wall being demolished to make way for an open kitchen
 We are going to reorientate the staircase storage door




 Going to rework the entrance of one of the upper floor bedrooms.
 warzone here in the bathroom. Does it look as if Wolverine has been down to site?
Bricklayer cum wall tiler is here too, need to confirm all the floor tile setting out, direction, pointing and where to start the walls etc.
Monster TREE looking branch pipeworks in the kitchen.