Sunday, September 28, 2014

Reno@Ancilla BTO - Cove lights and A/C up

hello there!
so sorry for the lack of updates on our Ancilla project last week cos hubs was so busy talking to the electrician that he forgot to snap some pictures! Anyway so this week the photos are double!!! So enjoy the quick progress tour.

Above: the new wall at the kitchen has been plastered and it's all ready for a new coat of white paint!
 The entire living room's cove lighs are completed already
 The air con was installed over the week too. All the A/C trunking are boxed up too.
New kitchen entrance, plastered up, ready for the door installation. But this will be at later stage cos the carpentry got to go in first! The bigger the opening, the easier it is for our carpentry carcass to go in. We wouldn't want to spoil our new lovely kitchen door with all the workmen going in and out!
New kitchen wall - fully tiled with the same original HDB wall tiles. You can't even tell that it's totally new!!
 Bedroom 3 - cove light holders are up. You might be wondering what is that loose piece of wire dangling from the ceiling. It's for the ceiling fan.
 Here's another view of the bedroom 3 with the new aircon unit above the door.
 common bath - new ceiling!!! No more ugly plastic grid things above my head!!!
 Bedroom 2 - Cove light holders completed
 Another view of Bedroom 2 - Aircon is up too!
Master bathroom - ceiling up! Small Aircon trunking which we can't hide. Can see? It's on the left of the small window!
 Master room - cove light and aircon up!
Goodness!! we are nearing to the end already!!!This week, the painting is going to start and then the carpentry is going to start off site and within the next 2-3 weeks, we will see the carpentry! So fast! Exciting times now.

Hope your weekend went well and stay tuned for more posts to come!!!

xoxo
velle

No comments:

Post a Comment

LinkWithin

Related Posts Plugin for WordPress, Blogger...