Saturday, January 18, 2014

Reno@Bukit Panjang Maisonette - Ceiling are almost up now

Hello there!
Here's another maisonette which we are currently working on and it's the one that has a splendid view towards a park and reservoir. Over the week, the contractor has been very busy with his electrician, laying out most of the electrical works and framing system for the false ceiling.
 Above: False ceiling almost completed in the master.


 Above: updates on the false ceiling and cove lights in the other 2 bedrooms.
Above: framing system at the staircase landing for cove lights to be flush up and down.
Think of it like what we usually do for the vanity mirror cabinets in the toilet but a bigger version of it here!!!
Newly created helper's room. Partition wall up, now what it needs is some plastering and a good paint job!
 Here's looking into the helper's room from the kitchen area.
Framing system for the false ceiling in the kitchen area up.
Next is waiting for the aircon installation.