Wednesday, April 29, 2015

Reno@Trivelis - electrical works

Here's our first DBSS project!
This week's happenings
1) Protective flooring done
2) Gone through one round with the electrician
3) All electrical works pulled
4) Gone through one round with the carpenter
5) Fabrication of carpentry in the factory

Target 2 weeks to start carpentry works here!
living and study area


master room


No comments:

Post a Comment


Related Posts Plugin for WordPress, Blogger...